Complete project support from product selection and engineering through manufacturing, inspection, delivery and site support.
Technical assistance, spare parts, maintenance coordination, troubleshooting and long-term product support.
Warranty coordination, inspection, repair, refurbishment, testing and replacement support for supplied products.
A closer look at major EPC, onshore, offshore and gas processing projects across the UAE where GULFTECH has supported leading operators and contractors with products, engineering and technical services.
Borouge 4 is one of the largest industrial projects underway in the UAE. Built by Borouge on behalf of the project’s owners, ADNOC and Borealis, it will boost production capacity by 1.4 million tonnes and make it the world’s largest single-site polyolefin complex. Once complete, it will enhance Borouge’s ability to meet growing global demand for innovative polyolefin solutions across energy, infrastructure and advanced packaging, while driving economic diversification, creating employment and supporting the growth of the UAE’s industrial base.
The MERAM project adds new facilities to recover ethane from residue gas at existing NGL Recovery Units, including Asab-0/3, Bab, Habshan 1 Trains 1, 2 & 3, Habshan 2, Habshan 5 (Lean Trains) and BuHasa. It also includes modifications to existing facilities to accommodate the HMP 4.0 production profile and new feed gas and product (NGL, sales gas) pipelines, meeting Borouge 4 demand of 2.0 MMTPA of sustainable raw ethane supply. Facilities are located mainly at the Habshan 5 gas processing plant, with pipelines between Habshan and Ruwais and interconnections to the sales gas network.
The Hail and Ghasha development design combines innovative decarbonization technologies into one integrated solution. The project will capture 1.5 million tonnes per year (mtpa) of CO2, while low-carbon hydrogen is produced that can replace fuel gas and further reduce emissions. The project will also leverage clean power from nuclear and renewable sources from the grid.
The project “EPC for Tie-in Works at SQM (Package-4)” was initiated to sustain and enhance oil production from the Shah, Qusahwira and Mender (SQM) fields, located approximately 200, 220 and 240 km south of Abu Dhabi city respectively. These fields are managed and operated by ADNOC Onshore.
This ADNOC Onshore project (Project ID 107105) focuses on repairing and improving the integrity of pipelines in the Bab and Asab oil fields. Key activities include replacing damaged flowlines, rerouting existing lines to reduce field congestion, and modifying supports to address issues such as buckling and dislocation. The project is part of a larger upgrade to minimize life-cycle costs and enhance the efficiency of the fields.
The Bab Integrated Facilities Project (BIFP) is an ADNOC Onshore project to upgrade and expand the Bab oil and gas field in Abu Dhabi, sustaining and enhancing its crude oil production capacity to at least 450,000–485,000 barrels per day. It involves constructing new processing facilities, upgrading existing ones, and implementing new technologies such as digital oil fields and cluster drilling to increase production and efficiency from the mature field.
The Bab oil field, also known as the Murban Bab oil field, is the biggest onshore oil field in Abu Dhabi at 1,200 km² and the oldest in the UAE, operating since the early 1960s. As part of ADNOC’s 2030 smart growth strategy, the field is being upgraded to sustain crude output of 485,000 barrels of oil per day from 2023 onwards. The EPC scope includes greenfield works with demanding logistics and brownfield works with their associated challenges. Surface facilities comprise 118 new oil-producing, water injection and artificial lift wells, 462 km of flowlines/trunk lines and 150 km of fiber optic cables, plus well-bays, pressure let-down stations, water injector clusters and associated infrastructure. Plant modifications include 80 km of piping, fire & gas detection and firewater systems.
The Buhasa De-Bottlenecking & Associated Piping Project for ADNOC Gas Processing aims to enhance the capacity and efficiency of the existing gas processing facilities at Bu Hasa. It involves modification and rerouting of process and utility pipelines, installation of new valves and tie-ins, upgrading instrumentation, and replacing critical equipment to eliminate operational bottlenecks — improving flow distribution, increasing throughput, and ensuring safe, reliable and optimized plant operations in line with ADNOC standards.
The LZ-LTDP-1 New Main Gas Line project is an ADNOC Offshore initiative focused on installing a new main gas pipeline to support the field’s long-term production and gas export capacity. It encompasses the engineering, procurement, construction and commissioning of the NMGL system, ensuring safe, efficient and reliable gas transportation from Lower Zakum facilities to onshore processing infrastructure, enhancing operational performance and supporting ADNOC’s strategic energy objectives.
This EPC project upgraded the Rim Seal Fire (RSF) and Full Surface Fire (FSF) fighting systems for the Crude Oil Storage (COS) tanks at Zirku Island to enhance fire safety and asset integrity. The scope included demolition of existing risers and bund fire protection piping, installation of new risers, pipe supports, foam skids and comprehensive FSF protection for tanks 1–6. A Corrosion Risk Assessment (CRA) ensured long-term integrity, and the systems provide early detection and suppression of fires in the rim seal zone and across the tank surface using foam or gas-based agents.
The Belbazem offshore project is an ADNOC initiative for full field development, awarded as an EPC contract in 2021. It includes constructing offshore wellhead towers, pipelines, and facilities for water injection and gas compression to produce crude oil and gas, utilizing synergies with existing facilities for cost and environmental benefits.
Phase III of the Al Dabb’iya project is part of ADNOC Onshore’s Northeast Bab (NEB) development program, located in a shallow coastal and marine area 40 km southwest of Abu Dhabi — an environmentally sensitive area with mangroves, coral reef, salt marshes and protected wildlife. The program adds 73,000 barrels of oil per day through gathering & injection systems, oil export and gas import/export pipelines. Works comprised gathering crude oil from onshore and offshore well clusters and transporting it through 100 km of offshore carbon steel pipelines to the central process plant, along with modular steel structures, 450,000 dia-inches of piping, 56 km of offshore cabling and dredging of pipeline corridors.
A call-out agreement under which a range of tie-in services are performed as needed at the Asab and Sahil fields. This includes engineering, procurement and construction (EPC) of new facilities, flowlines and connections to support oil production, designed to enhance the oil production capacity of the fields.
The project involves the procurement, fabrication and construction of flowlines and wellhead installations for Package-1, Part-1 at the Asab and Sahil fields. It encompasses detailed engineering, supply of materials and equipment, installation of wellhead structures, associated flowlines and tie-ins to existing infrastructure in compliance with ADNOC standards — including testing, commissioning and handover of fully operational systems to support enhanced hydrocarbon production.
The scope covers engineering, procurement and construction of two power skids at Jebel Dhana, including modification of various switchgears, additional isolation valves on inlet and outlet connections to small and medium tanks, and an RGA lightning system for tanks. It also covers implementation of Environmental Impact Assessment (EIA) study recommendations for ADCOP line block valve stations, IPS and MOT.
Al Dhafra Petroleum Operations Company is developing its concession Area A1, which includes the Haliba Main Body, Haliba North & South, Near Haliba Prospects (Al Humrah, Bu Tasa) and the East Area fields. The EPC works cover tie-ins of different well types, including oil producer wells, ESP artificial-lift oil producer wells, water injection, water supply and water disposal wells.
A selection of projects successfully delivered for leading organizations across the UAE.
| SL. NO. | CLIENT / CONSULTANT | PROJECT | YEAR |
|---|---|---|---|
| 1 | ADNOC ONSHORE | 4300 B4 U & O BOROUGE PROJECT | 2026 |
| 2 | ADNOC GAS | MAXIMIZE ETHANE RECOVERY & MONETIZATION (MERAM) – EPC | 2026 |
| 3 | ADNOC ONSHORE | HAIL AND GHASHA DEVELOPMENT PROJECT PACKAGE 2 – ONSHORE FACILITIES | 2026 |
| 4 | ADNOC ONSHORE | CALL-OUT SERVICES AGREEMENT FOR TIE-IN AT SHAH/QUSAHWIRA/MENDER (PART 2) | 2026 |
| 5 | ADNOC ONSHORE | REHABILITATION AND INTEGRITY REINSTATEMENT OF FLOW LINES AND TRUNK LINES IN BAB & ASAB PROJECT | 2026 |
| 6 | ADNOC GAS | FEEDSTOCK, UTILITIES AND INTERCONNECTING PIPELINES FOR TA’ZIZ INDUSTRIAL PARK | 2026 |
| 7 | ABU DHABI POLYMERS CO.LTD. (BOROUGE) | ABU DHABI POLYMER RUWAIS PLANT PROJECT | 2026 |
| 8 | ADNOC ONSHORE | EPC FOR NEB FACILITIES UPGRADE PROJECT | 2026 |
| 9 | ADNOC GAS | EPCM FOR LONG TERM FACILITIES – ASAB & BUHASA | 2026 |
| 10 | ADNOC ONSHORE | EPC FOR REHABILITATION AND INTEGRITY REINSTATEMENT OF FLOW LINES AND TRUNK LINES IN BAB & ASAB PROJECT | 2026 |
| 11 | ADNOC ONSHORE | ADNOC ONSHORE NEB FACILITIES UPGRADE PROJECT | 2026 |
| 12 | VOPAK HORIZON | VOPAK PROJECT | 2026 |
| 13 | ADNOC ONSHORE | CALL-OUT SERVICES AGREEMENT FOR TIE-IN AT SHAH-QUSAHWIRA MENDER (PART 4) | 2026 |
| 14 | CONSOLIDATED EDISON COMPANY OF NEW YORK (CONED) | ASTORIA LNG PROJECT USA | 2026 |
| 15 | ADNOC OFFSHORE | PROCUREMENT & CONSTRUCTION OF FACILITIES FOR MUBARRAZ REDEVELOPMENT PROJECT | 2026 |
| 16 | ADNOC DRILLING | ADNOC DRILLING PROJECT | 2026 |
| 17 | ADNOC ONSHORE | NITROGEN CYLINDER SKID PACKAGE FOR EPC FOR NEB FACILITIES UPGRADE PROJECT (P174) | 2026 |
| 18 | ADNOC GAS O&M LLC | ADNOC GAS PROJECT | 2026 |
| 19 | ADNOC OFFSHORE | LOWER ZAKUM PROJECT | 2026 |
| 20 | ABU DHABI POLYMERS | ADNOC PROJECT | 2026 |
| 21 | ADNOC ONSHORE | GAS DIVERSION PROJECT (VARIATION ORDER) – FAST-TRACK PROJECT | 2026 |
| 22 | ADNOC OFFSHORE | LOWER ZAKUM LONG TERM DEVELOPMENT PHASE – I (LZ-LTDP-1) NEW MAIN GAS LINE PROJECT | 2026 |
| 23 | ADNOC ONSHORE | CHEMICAL INJECTION SKID FOR EPC FOR AL DABBIYA THAMAMA B TRANSITION ZONE DEVELOPMENTS- PHASE II PROJECT | 2026 |
| 24 | ADNOC GAS | HABSHAN 1 TO CS3 – AG TIE IN – ADNOC | 2026 |
| 25 | ADNOC GAS | EPCM CONTRACT FOR THE HABSHAN DBN PROJECT | 2026 |
| 26 | ADVARIO | ADVARIO OMAN PROJECT | 2026 |
| 27 | ADNOC ONSHORE | EPC FOR NEB MISCELLANEOUS MODIFICATION AND ENHANCEMENT PROJECT | 2026 |
| 28 | NEOM COMPANY | NEOM GREEN HYDROGEN PROJECT (G2HO) | 2026 |
| 29 | ADNOC ONSHORE | ADNOC ONSHORE – EPC CALL-OUT OF BAB ARTIFICIAL LIFT PHASE-II PROJECT | 2026 |
| 30 | ADNOC ONSHORE | CALL OUT SERVICES AGREEMENT FOR TIE IN AT SHAH/QUSAHWIRA MENDER (PACKAGE 4) | 2026 |
| 31 | ADNOC ONSHORE | WEST EAST PIPE LINE (WEP) PROJECT | 2026 |
| 32 | FUJAIRAH OIL TANKER TERMINALS (FOTT) | FOTT UPGRADATION WORKS | 2026 |
| 33 | ADNOC GAS | PROJECT P5.0 – EPCM FOR HABSHAN DBN | 2026 |
| 34 | ADNOC ONSHORE | ADNOC ONSHORE – CALL OUT SERVICES AGREEMENT FOR TIE IN AT SHAH/QUSAHWIRA MENDER (PART 2) -PROJECT NO.P30380 | 2026 |
| 35 | ADNOC GAS | HABSHAN 0 BOILERS UPGRADE PROJECT – PROJECT NO:50021 | 2026 |
| 36 | ADNOC ONSHORE | REHABILITATION AND INTEGRITY REINSTATEMENT OF FLOW LINES AND TRUNK LINES IN BAB & ASAB PROJECT | 2025 |
| 37 | ADNOC ONSHORE | KENT BAB PROJECT | 2025 |
| 38 | AL DHAFRA PETROLEUM | AL DHAFRA PETROLEUM PROJECT | 2025 |
| 39 | ADNOC ONSHORE | BAB INTEGRATED FACILITIES PROJECT | 2025 |
| 40 | ADNOC ONSHORE | PROVISION OF PLANT SHUTDOWN ACTIVITIES AT NEB & SE FIELDS | 2025 |
| 41 | ADNOC ONSHORE | CALL-OUT SERVICES AGREEMENT FOR TIE-IN AT SHAH/QUSAHWIRA/MENDER PACKAGE 4 – BATCH 2 WELLS | 2025 |
| 42 | ADNOC GAS | ESTIDAMA SALES GAS PIPELINE NETWORKS – PACKAGE 4 & 7 | 2025 |
| 43 | ADNOC ONSHORE | CALL-OUT SERVICES AGREEMENT FOR TIE-IN AT SHAH/QUSAHWIRA/MENDER PACKAGE 4 – BATCH 1 WELLS | 2025 |
| 44 | ADNOC ONSHORE | EPC OF SAHIL PHASE III DEVELOPMENT PROJECT | 2025 |
| 45 | EMIRATES STEEL | EMIRATES STEEL PROJECT | 2025 |
| 46 | BOROUGE | BOROUGE PROJECT | 2025 |
| 47 | ADNOC GAS | MAXIMIZE ETHANE RECOVERY & MONETIZATION (MERAM) – EPC | 2025 |
| 48 | ADNOC ONSHORE | CALL-OUT SERVICES AGREEMENT FOR TIE-IN AT ASAB-SAHIL (PART 2) – PKG 3 | 2025 |
| 49 | ADVARIO TERMINALS LLC | C1 PROJECT | 2025 |
| 50 | VOPAK | VHFL PROJECT | 2025 |
| 51 | AL DHAFRA PETROLEUM | AL DHAFRA PETROLEUM PROJECT – CONSTRUCTION WORKS FOR HALIBA WELL TIE INS FOR MAIN BODY & NEAR HALIBA PROSPECTS | 2025 |
| 52 | ADNOC ONSHORE | CALL-OUT SERVICES AGREEMENT FOR TIE-IN AT SHAH, QUSAHWIRA & MENDER (PKG-4) | 2025 |
| 53 | ADNOC ONSHORE | CALL-OUT SERVICES AGREEMENT FOR TIE-IN AT SHAH/QUSAHWIRA/MENDER (PART 2) | 2025 |
| 54 | FUJAIRAH OIL TANKER TERMINALS (FOTT) | CONNECTION TO FOTT MM1 BUNKER JETTIES | 2025 |
| 55 | ADNOC GAS | MIRFA PLANT MODIFICATION AND PIPELINE PROJECT | 2025 |
| 56 | AL DHAFRA PETROLEUM | TIE-INS OF WELLS IN HALIBA AND OTHER FIELDS (EPC WORKS) | 2025 |
| 57 | FUJAIRAH OIL TANKER TERMINALS (FOTT) | VHFL- CONNECTION TO FOTT MM1 BUNKER JETTIES | 2025 |
| 58 | ADNOC ONSHORE | J217 – EPC CALL-OUT OF BAB ARTIFICIAL LIFT PHASE-II PROJECT (P168 / P11671) | 2025 |
| 59 | ADNOC ONSHORE | EPC FOR MODIFICATION WORKS AT TPO AND GAS FIELDS | 2025 |
| 60 | ADNOC REFINING | J736 – UPGRADE RAW ETHANE EXPORT TO ADNOC REFINING & HEPTANE BLENDING FLOW METERS AT RUWAIS NGL, ABU DHABI PROJECT | 2025 |
| 61 | MODON | GHANTOOT DEVELOPMENT PROJECT – SITE CLEARANCE WORKS BY MODON | 2025 |
| 62 | AZULE ENERGY | AGOGO FPSO PROJECT | 2025 |
| 63 | ADNOC REFINING | HYDROCRACKER REVAMP PROJECT | 2025 |
| 64 | ADNOC ONSHORE | EPCM FOR UPGRADE OF ADCOP FACILITIES TO CATER 2.0 MMBOPD PROJECT | 2025 |
| 65 | ADNOC ONSHORE | 1828- EPCM FOR BAB FAR NORTH FULL FIELD DEVELOPMENT PROJECT (BFN) | 2025 |
| 66 | ADNOC ONSHORE | CALL-OUT SERVICES AGREEMENT FOR TIE-IN AT SHAH, QUSAHWIRA & MENDER (PART 1) | 2025 |
| 67 | ADNOC GAS | HABSHAN & BAB CONTROL SYSTEMS UPGRADE PROJECT (PACKAGE 1) | 2025 |
| 68 | ADNOC ONSHORE | PROJECT-REHABILITATION AND INTEGRITY REINSTATEMENT OF FLOW LINES AND TRUNK LINES IN BAB & ASAB PROJECT | 2025 |
| 69 | ADNOC GAS | ESTIDAMA SALES GAS PIPELINE NETWORKS – EWEC PHASE -1 | 2025 |
| 70 | VTTI FUJAIRAH | VTTI PROJECT | 2025 |
| 71 | ADNOC OFFSHORE | HAIL & GASHA PROJECT | 2025 |
| 72 | ADNOC ONSHORE | CALL – OUT SERVICES AGREEMENT FOR TIE-IN AT SHAH/QUSAHWIRA/MENDER PACKAGE 4 | 2025 |
| 73 | ADNOC ONSHORE | EPC FOR BAB FACILITIES UPGRADE PROJECT | 2025 |
| 74 | BROOGE PETROLEUM AND GAS INVESTMENT COMPANY (BPGIC) | BPGIC PROJECT | 2025 |
| 75 | ADNOC GAS | MAXIMIZE ETHANE RECOVERY & MONETIZATION (MERAM) | 2025 |
| 76 | ADNOC ONSHORE | EPC CALL-OUT OF BAB ARTIFICIAL LIFT PHASE-II PROJECT | 2025 |
| 77 | ADNOC OFFSHORE | HAIL & GASHA PROJECT PACKAGE 2 | 2025 |
| 78 | ADNOC GAS | MERAM PROJECT | 2025 |
| 79 | INTERNATIONAL MARITIME ORGANIZATION | IMO 2020 PROJECT | 2025 |
| 80 | ADNOC ONSHORE | EPC FOR NEB FACILITIES UPGRADE PROJECT | 2025 |
| 81 | ADNOC OFFSHORE | MUBARRAZ REDEVELOPMENT PROJECT | 2025 |
| 82 | ADNOC ONSHORE | CALL-OUT SERVICES AGREEMENT FOR TIE-IN AT SHAH/QUSAHWIRA/MENDER PART 4 | 2025 |
| 83 | ADNOC OFFSHORE | ADNOC OFFSHORE PROJECT | 2024 |
| 84 | ADNOC ONSHORE | CONSTRUCTION OF FLOWLINES & WELLHEAD TIE IN INSTALLATIONS IN BAB & NEB FIELD (PACKAGE 6) -FOR ON PAD WELLS _ P7099 | 2024 |
| 85 | ADNOC ONSHORE | EPC FOR ADCOP REMAINING WORKS AT MOT, MPS, AND IPS – (PACKAGE 1 & 2) | 2024 |
| 86 | ADNOC GAS PROCESSING | ADNOC GAS PROJECT | 2024 |
| 87 | GALFAR ENGINEERING | GALFAR ENGINEERING PROJECT | 2024 |
| 88 | SK ENGINEERING AND CONSTRUCTION | EPC FOR M PROJECT – SEEPAGE WATER TREATMENT PACKAGE | 2024 |
| 89 | PETRONAS | SABAH FLNG PROJECT | 2024 |
| 90 | ADNOC L&S | ADNOC L&S PROJECT | 2024 |
| 91 | ADNOC GAS | HABSHAN & BAB CONTROL SYSTEM UPGRADE | 2024 |
| 92 | ARABIAN INDUSTRIES | ARABIAN INDUSTRIES PROJECT | 2024 |
| 93 | ADNOC ONSHORE | EPC FOR MODIFICATION WORKS AT TPO AND GAS FIELDS | 2024 |
| 94 | ADNOC ONSHORE | EPC FOR NEB MISCELLANEOUS MODIFICATIONS AND ENHANCEMENTS PROJECT | 2024 |
| 95 | ADNOC ONSHORE | ADNOC ONSHORE PROJECT | 2024 |
| 96 | ROCKFIN | ROCKFIN PROJECT | 2024 |
| 97 | ADNOC GAS | MERAM PROJECT | 2024 |
| 98 | ADNOC ONSHORE | EPC FOR NEB MISCELLANEOUS MODIFICATIONS (P 12566) /ADNOC ONSHORE/PR FOR QOC | 2024 |
| 99 | ADNOC ONSHORE | EPC FOR BAB FACILITIES UPGRADE PROJECT P-151-PIG LAUNCHER & RECEIVERS MAXIMISATION PROJECT | 2024 |
| 100 | ADNOC REFINING | PROVISION OF NEW SLURRY PUMP, GAS CON C3 RECOVERY IMPROVEMENT & NEW STEAM REBOILER ALONG WITH ASSOCIATED FACILITIES AT RFCC UNIT RR-I | 2024 |
| 101 | ADNOC ONSHORE | SWIC (SIMPLIFIED WATER INJECTION CLUSTERS) FLOWLINES PROJECT | 2024 |
| 102 | ADNOC ONSHORE | EPC FOR VO-02,AL NOUF EXPORT GAS MAXIMISATION PROJECT | 2024 |
| 103 | EMIRATES STEEL | EMIRATES STEEL PROJECT | 2024 |
| 104 | CONSOLIDATED EDISON COMPANY OF NEW YORK (CONED) | ASTORIA LNG | 2024 |
| 105 | ADNOC ONSHORE | BIFP PROJECT | 2024 |
| 106 | ADNOC ONSHORE | EPCM FOR FUJAIRAH BUSINESS CONTINUITY PROJECT CONSTRUCTION WORK PACKAGE | 2024 |
| 107 | ADNOC OFFSHORE | EPC FOR RSF (RIM SEAL FOAM) AND FSF (FULL SURFACE FIRE) FIGHTING SYSTEM UPGRADE FOR COS TANKS AT ZIRKU | 2024 |
| 108 | ADNOC GAS | SAMPLING SYSTEM & CBA REACTOR UPGRADE PROJECT | 2024 |
| 109 | ADNOC OFFSHORE | SARB ACCELERATED GROWTH PROJECT _PACKAGE 01 | 2024 |
| 110 | ADNOC GAS | MAXIMIZE ETHANE RECOVERY & MONETIZATION (MERAM) – EPC | 2024 |
| 111 | ECOMAR | ECOMAR TERMINAL PHASE 1 PROJECT IN FUJAIRAH | 2024 |
| 112 | ASICO | ASICO PROJECT | 2024 |
| 113 | ADNOC ONSHORE | 1828- EPCM FOR BAB FAR NORTH FULL FIELD DEVELOPMENT PROJECT (BFN) | 2024 |
| 114 | ADNOC GAS | RUWAIS NGL-TRAINS MODIFICATIONS TO SUPPLY BOROUGE-4 FEED STOCK | 2024 |
| 115 | ASTORIA | ASTORIA PROJECT | 2024 |
| 116 | ADNOC OFFSHORE | EPC WORK OFFSHORE SITE SCHEMES PROJECT – UPPER ZAKUM FIELD | 2024 |
| 117 | ADNOC ONSHORE | CALL-OUT SERVICES AGREEMENT FOR TIE-IN AT SHAH/QUSAHWIRA/MENDER PACKAGE 4 – BATCH 1 WELLS | 2024 |
| 118 | NORTH OIL COMPANY, QATAR | RUYA PROJECT | 2024 |
| 119 | AL DHAFRA PETROLEUM | AL DHAFRA PETROLEUM PROJECT CONSTRUCTION WORKS FOR HALIBA WELL TIE INS FOR MAIN BODY & NEAR HALIBA PROSPECTS | 2024 |
| 120 | ADNOC ONSHORE | EPC FOR BAB GAS COMPRESSION PROJECT (BGCP) PHASE III | 2024 |
| 121 | METALFAB | EPCM FOR BAB FAR NORTH FULL FIELD DEVELOPMENT PROJECT (BFN) | 2024 |
| 122 | ADNOC ONSHORE | PROVISION OF PLANT SHUTDOWN ACTIVITIES AT NEB & SE FIELDS | 2024 |
| 123 | ADNOC OFFSHORE | HAIL AND GHASHA DEVELOPMENT PROJECT PACKAGE 2 -ONSHORE FACILITIES | 2024 |
| 124 | ADNOC REFINING | TAKREER RUWAIS – 3 MOC’S PROJECT | 2024 |
| 125 | AL DHAFRA PETROLEUM | CONSTRUCTION WORKS FOR HALIBA WELLS TIE-INS FOR MAIN BODY & NEAR HALIBA PROJECT | 2024 |
| 126 | ADVARIO | ADVARIO PROJECT | 2024 |
| 127 | ADNOC GAS O&M LLC | ADNOC GAS PROJECT | 2024 |
| 128 | ADNOC ONSHORE | CALL-OUT SERVICES AGREEMENT FOR TIE-IN AT ASAB-SAHIL (PART 2) – PKG 3 | 2024 |
| 129 | ADNOC ONSHORE | CALL-OUT SERVICES AGREEMENT FOR TIE-IN AT SHAH, QUSAHWIRA & MENDER (PART 1) | 2024 |
| 130 | ADNOC ONSHORE | EPC FOR UPGRADATION OF FACILITIES AT SE FIELDS | 2024 |
| 131 | HKN ENERGY | ST-B3, SARSANG OILFIELD | 2024 |
| 132 | ADNOC POLYMERS | ADNOC PROJECT | 2024 |
| 133 | BOROUGE | BOROUGE 4 PROJECT | 2024 |
| 134 | ADNOC ONSHORE | EPC OF SAHIL PHASE III DEVELOPMENT PROJECT | 2024 |
| 135 | ADNOC ONSHORE | REHABILITATION AND INTEGRITY REINSTATEMENT OF FLOW LINES AND TRUNK LINES IN BAB & ASAB PROJECT | 2024 |
| 136 | ADNOC GAS | ESTIDAMA SALES GAS PIPELINE NETWORKS – PACKAGE 4 & 7 | 2024 |
| 137 | ADNOC GAS | MIRFA PLANT MODIFICATION AND PIPELINE – EPC WORK PROJECT NO-5374 | 2024 |
| 138 | ARAMCO | FADHILI (GAS INCREMENT PROGRAM PROJECT) | 2024 |
| 139 | ADNOC ONSHORE | CONSTRUCTION OF FLOW LINES AND WELL HEAD TIE-INS AT BAB/NEB FIELD | 2024 |
| 140 | ADNOC ONSHORE | EPC FOR BAB GAS COMPRESSION PHASE III PROJECT | 2023 |
| 141 | NPCC | NPCC PROJECT | 2023 |
| 142 | ADNOC ONSHORE | BAB FACILITY UPGRADE PROJECT | 2023 |
| 143 | ADNOC OFFSHORE | EPC WORKS OFFSHORE SITE SCHEME PROJECT – UZ FIELDS | 2023 |
| 144 | AZULE ENERGY | AGOGO FPSO PROJECT | 2023 |
| 145 | ADNOC ONSHORE | BAB GAS COMPRESSION PHASE III | 2023 |
| 146 | VOPAK | VOPAK PROJECT | 2023 |
| 147 | ADNOC GAS & ADNOC REFINING | RUWAIS POTABLE WATER SYSTEM UPGRADE TRAIN 1 & TRAIN 2 PROJECT | 2023 |
| 148 | FEWA (ETIHADWE) | HORIZON-FEWA POWER CONNECTION AT JEFF THE PROJECT | 2023 |
| 149 | AL DHAFRA PETROLEUM | AL DHAFRA PETROLEUM PROJECT – CONSTRUCTION WORKS FOR HALIBA WELL TIE INS FOR MAIN BODY & NEAR HALIBA PROSPECTS | 2023 |
| 150 | ADNOC OFFSHORE | MUBARAZ ISLAND PROJECT | 2023 |
| 151 | EMIRATES STEEL | EMIRATES STEEL PROJECT | 2023 |
| 152 | OIL TANKING TERMINALS & CO | OIL TANKING TERMINALS & CO PROJECT | 2023 |
| 153 | ADNOC ONSHORE | PROCUREMENT AND CONSTRUCTION OF FLOWLINES AND WELLHEAD INSTALLATIONS AT SQM – SHAH, QUASAWIRA & MENDER (PACKAGE-2, PART-1) | 2023 |
| 154 | ADVARIO | ADVARIO PROJECT | 2023 |
| 155 | ADNOC ONSHORE | PROCUREMENT AND CONSTRUCTION OF FLOWLINES AND WELLHEAD INSTALLATIONS AT ASAB AND SAHIL (PACKAGE-1, PART-1) | 2023 |
| 156 | JOHN ZINK | JOHN ZINK PROJECT | 2023 |
| 157 | BASRA OIL COMPANY (BOC) | BOC MAJNOON (P&M) PROJECT, KBR, IRAQ | 2023 |
| 158 | ADNOC REFINING | UPGRADE RAW ETHANE EXPORT TO ADNOC REFINING & HEPTANE BLENDING FLOW METERS – RUWAIS NGL | 2023 |
| 159 | ADNOC OFFSHORE | EPC WORK OFFSHORE SITE SCHEMES PROJECT | 2023 |
| 160 | ADNOC OFFSHORE | UPPER ZAKUM FIELD | 2023 |
| 161 | ADNOC OFFSHORE | RFS (RIM SEAL FIRE) AND FSF (FULL SURFACE FIRE) FIGHTING SYSTEM UPGRADE FOR COS TANKS AT ZIRKU | 2023 |
| 162 | ADNOC ONSHORE | SWIC FLOWLINES (PKG-1 & PKG-2) PROJECT | 2023 |
| 163 | ADNOC ONSHORE | ADNOC ONSHORE PROJECT | 2023 |
| 164 | PROBUS ENGINEERING | PROBUS ENGINEERING PROJECT | 2023 |
| 165 | ADNOC GAS & ADNOC ONSHORE | BUHASA PLANT FOR UPGRADE PROJECT | 2023 |
| 166 | ADNOC GAS PROCESSING | BGCP PROJECT | 2023 |
| 167 | ABU DHABI CRUDE OIL PIPELINE (ADCOP) | EPC FOR ADCOP REMAINING WORKS AT MOT, IPS & MPS | 2023 |
| 168 | LINKS MIDDLE EAST | LINKS MIDDLE EAST PROJECT | 2023 |
| 169 | ADNOC OFFSHORE | LOWER ZAKUM LONG TERM DEVELOPMENT PHASE-1 (LZ-LTDP-1) NEW MAIN GAS LINE (NMGL) PROJECT | 2023 |
| 170 | ADNOC | M PROJECT-SKEC | 2023 |
| 171 | ADNOC ONSHORE | TECHNICAL SERVICES AGREEMENT (CALL-OFF) FOR BU HASA TIE-INS (P12516) – TASK ORDER 4 (TO4) | 2023 |
| 172 | ADNOC SOUR GAS | EPC WORKS FOR INSTALLATION OF ADDITIONAL REFRIGERANT CONDENSERS IN UNITS 0730/0741/0742 | 2023 |
| 173 | PORT OF FUJAIRAH | FOT PROJECT | 2023 |
| 174 | VOPAK | VHFL PROJECT | 2023 |
| 175 | ADNOC ONSHORE | EPC FOR BU HASA WATER INJECTION RECOVERY PROJECT | 2023 |
| 176 | PETRONAS | SABAH FLNG PROJECT | 2023 |
| 177 | BOROUGE | BOROUGE PROJECT | 2023 |
| 178 | ADNOC ONSHORE | PROCUREMENT & CONSTRUCTION OF FLOWLINES AND WELLHEAD INSTALLATIONS AT ASAB & SAHIL [PART-2] PACKAGE-1 | 2023 |
| 179 | ADNOC ONSHORE | EPC FOR MISCELLANEOUS WORKS AT TPO, P150 | 2023 |
| 180 | BOROUGE | BOROUGE 4 PROJECT | 2023 |
| 181 | PETROCHEM MIDDLE EAST | PETROCHEMICAL TERMINAL AT PLOT B052F02 PROJECT | 2023 |
| 182 | ADNOC ONSHORE | TANK REFURBISHMENT PROJECT – FOR TANK T1510 | 2022 |
| 183 | ABU DHABI PORTS GROUP (AD PORTS / ADPC) / ADNOC ONSHORE | DESIGN AND CONSTRUCTION OF KIZAD GAS NETWORK PHASE-2 | 2022 |
| 184 | ADNOC ONSHORE | BAB INTEGRATED FACILITIES PROJECT (BIFP) | 2022 |
| 185 | ADOC | MUBARRAZ OIL FIELD REDEVELOPMENT PROJECT | 2022 |
| 186 | ADNOC OFFSHORE | EPC WORK OFFSHORE SITE SCHEMES PROJECT – UPPER ZAKUM FIELD PROJECT | 2022 |
| 187 | ADNOC GAS | RUWAIS POTABLE WATER SYSTEM UPGRADE TRAIN 1 & TRAIN 2 | 2022 |
| 188 | ADNOC DRILLING | ESTIDAMA SALES GAS PIPELINE NETWORK ENHANCEMENT PACKAGE1 | 2022 |
| 189 | SARSAN HEAVY ENGINEERING (FZE) | NIGERIA PROJECT | 2022 |
| 190 | ADNOC ONSHORE | BAB 485 MBD SUSTAINABLE FACILITIES PROJECT | 2022 |
| 191 | PETROCHEM | PETROCHEMICAL TERMINAL AT PLOT B052F02 | 2022 |
| 192 | PETROBRAS | MARIA QUITERIA PROJECT – BRAZIL | 2022 |
| 193 | ENOC | ENOC PROJECT | 2022 |
| 194 | ADNOC ONSHORE | NITROGEN SKID PACKAGE – DABBIYA THAMAMA TRANSITION ZONE B PROJECT – PHASE II | 2022 |
| 195 | ISSCO | MUBARRAZ OIL FIELD REDEVELOPMENT PROJECT | 2022 |
| 196 | ADNOC ONSHORE | PROCUREMENT AND CONSTRUCTION OF FLOWLINES AND WELLHEAD INSTALLATIONS AT ASAB AND SAHIL (PACKAGE-1, PART-1) | 2022 |
| 197 | ADNOC ONSHORE | PROCUREMENT AND CONSTRUCTION OF FLOWLINES AND WELLHEAD INSTALLATIONS AT SQM – SHAH, QUASAWIRA & MENDER (PACKAGE-2, PART-1) | 2022 |
| 198 | FUJAIRAH OIL TERMINAL (FOT) | FOT – VLCC CONNECTIVITY | 2022 |
| 199 | PORT OF FUJAIRAH (POF) | POF PROJECT | 2022 |
| 200 | VOPAK HORIZON | VOPAK HORIZON FUJAIRAH LIMITED (VHFL) PROJECT | 2022 |
| 201 | ADNOC ONSHORE | EPC FOR BAB 485 MBOPD SUSTAINABLE FACILITIES PROJECT | 2022 |
| 202 | ARABIAN CHEMICAL TERMINALS COMPANY LLC (ACTAD) | EPC OF GREENFIELD CHEMICAL TERMINAL PROJECT IN KIZAD | 2022 |
| 203 | MIRFA INTERNATIONAL POWER & WATER COMPANY (MIPCO) | MIPCO PROJECT | 2022 |
| 204 | AL DHAFRA PETROLEUM | CONSTRUCTION WORKS FOR HALIBA WELLS TIE-INS FOR MAIN BODY & NEAR HALIBA PROSPECTS | 2022 |
| 205 | ADNOC OFFSHORE | ADNOC OFFSHORE PROJECT | 2022 |
| 206 | AL DHAFRA PETROLEUM | AL DHAFRA PETROLEUM PROJECT – CONSTRUCTION WORKS FOR HALIBA WELL TIE INS FOR MAIN BODY & NEAR HALIBA PROSPECTS | 2022 |
| 207 | FUJAIRAH OIL TERMINAL FZC | FUJAIRAH OIL TERMINAL FZC PROJECT | 2022 |
| 208 | EMIRATES STEEL | EMIRATES STEEL PROJECT | 2022 |
| 209 | BANDUQ COMPANY | BANDUQ PROJECT | 2022 |
| 210 | ABU DHABI PORTS GROUP (AD PORTS / ADPC) / ADNOC ONSHORE | DESIGN AND CONSTRUCTION OF KIZAD GAS NETWORK – PHASE 2 PROJECT | 2022 |
| 211 | ADNOC ONSHORE | ASAB GAS INJECTION TRUNK LINE-2 RELOCATION PROJECT | 2022 |
| 212 | BOROUGE | BOROUGE PROJECT | 2022 |
| 213 | ADNOC ONSHORE | ADNOC ONSHORE PROJECT | 2022 |
| 214 | VTTI | VTTI PROJECT | 2022 |
| 215 | ADCO | ADCO TIE INS PROJECT PACKAGE B | 2016 |
| 216 | ABU DHABI JAPAN OIL CO. (ADOC) | MUBARAZ ISLAND OFFSHORE MAINTENANCE PROJECT | 2016 |
| 217 | ADMA OPCO | AGFA PROJECT | 2016 |
| 218 | ADCO | REFURBISHMENT OF TANK FARM IN JEBEL DHANNA TERMINAL PROJECT | 2016 |
| 219 | ADCO | EPC FOR SAHIL FIELD DEVELOPMENT PROJECT PHASE 2 PROJECT | 2016 |
| 220 | ADCO | BUHASA PROJECT | 2016 |
| 221 | ADCO | FLOW LINES AND WELLHEADS BUHASA PROJECT-BU741 | 2016 |
| 222 | ADCO | EPC FOR RUMAITHA NORTH CO2 INJECTION PROJECT | 2016 |
| 223 | ADCO | EPC FOR BAB FAR NORTH CO2 INJECTION PROJECT | 2016 |
| 224 | ADCO | CONSTRUCTION OF MPP, MSMS & MPFMS AT BUHASA RDSS PROJECT | 2016 |
| 225 | ADCO | NEW WAG WELLS & CONVERSION OF EXISTING OF GAS INJECTORS WELLS TO WAG WELLS AT SAHIL | 2016 |
| 226 | STAR ENERGY OIL TANKING | SEOT PHASE 7A POLYOLS STORAGE AND HANDLING PROJECT | 2016 |
| 227 | PORT OF FUJAIRAH | POF FOR THE BERTH 3 EXPANSION WORKS | 2016 |
| 228 | PORT OF FUJAIRAH | BPGIC PHASE 1 PROJECT | 2016 |
| 229 | BROOGE PETROLEUM & GAS INVESTMENT COMPANY FZC (BPGIC) | BPGIC FUJAIRAH TERMINAL-PHASE 1 | 2016 |
| 230 | ECOMAR ENERGY SOLUTIONS | PETROLEUM REGENERATION & PROCESSING FACILITY TANK FARM | 2016 |
| 231 | PORT OF FUJAIRAH | PORT OF FUJAIRAH PROJECT | 2016 |
| 232 | PORT OF FUJAIRAH | POF – VLCC JETTY NO.1 PROJECT | 2016 |
| 233 | ALBANNA ENGINEERING | GPC- HAMRIYAH TANK FARM EXPANSION PROJECT | 2016 |
| 234 | ABU DHABI JAPAN OIL CO. (ADOC) | MUBARAZ ISLAND OFFSHORE MAINTENANCE PROJECT | 2015 |
| 235 | SHARJAH NATIONAL LUBE OIL (SHARLU) | SHARJAH NATIONAL LUBE OIL PROJECT | 2015 |
| 236 | PORT OF FUJAIRAH | POF – MM2 CONNECTIVITY FOR OT2 PIPELINES | 2015 |
| 237 | FUJAIRAH OIL TERMINAL – FOT | FUJAIRAH OIL TERMINAL PROJECT | 2015 |
| 238 | PORT OF FUJAIRAH | PORT OF FUJAIRAH PROJECT | 2015 |
| 239 | ABU DHABI JAPAN OIL CO. (ADOC) | MUBARAZ ISLAND OFFSHORE MAINTENANCE PROJECT | 2014 |
| 240 | ADMA OPCO | SARB 3 OFFSHORE FULL FIELD DEVELOPMENT PROJECT | 2014 |
| 241 | ZADCO | OFFSHORE WELL HEAD PROJECT – UMM AL DHAK FACILITIES FOR WHP 7 & 15 | 2014 |
| 242 | ADCO | PRODUCTION MANIFOLD AT RDS1 & RDS5 | 2014 |
| 243 | ABU DHABI JAPAN OIL CO. (ADOC) | MUBARAZ ISLAND OFFSHORE MAINTENANCE PROJECT | 2014 |
| 244 | DUBAI NATURAL GAS COMPANY LIMITED – DUGAS | DUGAS PROJECT | 2014 |
| 245 | FUJAIRAH OIL TERMINAL – FOT | FUJAIRAH OIL TERMINAL PROJECT | 2014 |
| 246 | PORT OF FUJAIRAH | OT2 PHASE II TOP SIDE FACILITY PROJECT | 2014 |
| 247 | PORT OF FUJAIRAH | PORT OF FUJAIRAH PROJECT | 2014 |
| 248 | PORT OF FUJAIRAH | POF OT2 PHASE II PROJECT | 2014 |
| 249 | ZADCO | OFFSHORE WHP TWINNING PROJECT AT UMM AL DHAK | 2014 |
| 250 | ATS TERMINAL | OIL TERMINAL PROJECT – HAMRIYA | 2014 |
| 251 | ILFS TERMINAL | ILFS OIL TERMINAL – FUJAIRAH | 2014 |
| 252 | DUGAS | JEBEL ALI PLANT FIRE WATER SYSTEM | 2014 |
| 253 | SHARAFCO PETROLEUM FZ | SHARAFCO STORAGE TERMINAL HAMRIYAH FREEZONE PROJECT | 2014 |
| 254 | FUJAIRAH OIL TERMINAL – FOT | FUJAIRAH OIL TERMINAL PROJECT | 2014 |
| 255 | ABU DHABI JAPAN OIL CO. (ADOC) | MUBARAZ ISLAND OFFSHORE MAINTENANCE PROJECT | 2013 |
| 256 | ADMA OPCO / TECHNIP | FLARES MODIFICATION REVAMP PROJECT | 2013 |
| 257 | LAMPRELL | RAK GAS COMPANY | 2013 |
| 258 | FRCL – REFINERY – UAE | FRCL PROJECT, FUJAIRAH | 2013 |
| 259 | DUGAS | JEBEL ALI PLANT FIRE WATER SYSTEM | 2013 |
| 260 | GULF PETROCHEM | GULF PETROCHEM PROJECT, FUJAIRAH | 2013 |
| 261 | DNO | DNO PROJECT SHJM | 2013 |
| 262 | VHFL | SPM PIPELINE MODIFICATION IN MANIFOLD PROJECT | 2013 |
| 263 | ENOC | ENOC FUJAIRAH TRADING TERMINAL PROJECT | 2013 |
| 264 | STEVENS SUPPLY INTL | SHIP – LINE BLIDING | 2013 |
| 265 | ABU DHABI JAPAN OIL CO. (ADOC) | MUBARAZ ISLAND OFFSHORE MAINTENANCE PROJECT | 2012 |
| 266 | ADMA OPCO | OFFSHORE – REPLACEMENT OF 30″ ZK STRIPPER | 2012 |
| 267 | ADCO | THAMAMA ‘G’ & HABSHAN 2 DEVELOPMENT PROJECT | 2012 |
| 268 | BOROUGE | BOROUGE PLANT | 2012 |
| 269 | EMIRATES ALUMINIUM (EMAL) | EMAL PROJECT, TAWEELAH ABU DHABI | 2012 |
| 270 | ABU DHABI JAPAN OIL CO. (ADOC) | MUBARAZ ISLAND OFFSHORE MAINTENANCE PROJECT | 2011 |
| 271 | EMIRATES ALUMINIUM (EMAL) / SNC LAVLIN | EMIRATES ALUMINUM SMELTER COMPLEX PLANT WIDE UNDERGROUND PROJECT, TAWEELAH ABU DHABI | 2010 |
| 272 | ABU DHABI JAPAN OIL CO. (ADOC) | MUBARAZ ISLAND OFFSHORE MAINTENANCE PROJECT | 2010 |
| 273 | ABU DHABI JAPAN OIL CO. (ADOC) | MUBARAZ ISLAND OFFSHORE MAINTENANCE PROJECT | 2009 |
| 274 | EMIRATES ALUMINIUM (EMAL) / SNC LAVLIN | EMIRATES ALUMINUM SMELTER COMPLEX PLANT WIDE UNDERGROUND PROJECT, TAWEELAH ABU DHABI | 2009 |